Energiequelle Expands Krummensee Wind Farm with a Modern 4.2 MW Turbine
Following a long journey from permitting to implementation, the new wind turbine is now supplying climate-friendly electricity to the grid in Brandenburg, GermanyEnergiequelle GmbH has successfully commissioned another wind turbine in the Barnim district of Brandenburg, Germany. With the delivery of the first kilowatt-hour, the company is expanding its existing wind farm with a state-of-the-art Enercon E-138 EP3 E2 turbine, featuring a hub height of 160 meters and an installed capacity of 4.2 megawatts.
The new turbine is located within the Krummensee priority area for wind energy development in the municipality of Werneuchen and complements the existing wind farm, where projects such as Krummensee IV had previously been realised. A site quality factor of nearly 80 percent highlights the favourable wind conditions at the location and provides a solid foundation for reliable long-term electricity generation from renewable energy sources.
However, the path to commissioning was longer than originally anticipated. The environmental permit for the project was granted as early as July 2021. Due to legal proceedings, implementation of the project was significantly delayed. To ensure the continued validity of the permit, an extension notice was issued in July 2024.
Following the resolution of the legal dispute, preparatory construction activities began in September 2024. These included archaeological investigations, the recovery of archaeological artefacts, and the construction of access roads and work areas. With the start of foundation works in March 2025, the actual construction of the wind turbine commenced.
In addition to renewable energy generation, nature conservation also played an important role in the project. As a compensatory measure, a crane habitat was created by rewetting a natural depression in an agricultural field, thereby establishing a water body and adjacent foraging area.
"This project has accompanied us for many years and repeatedly presented us with new challenges. We are therefore all the more pleased that the turbine has now been successfully commissioned. Our sincere thanks go to all colleagues, partners, authorities, and service providers whose commitment and perseverance contributed to the success of this special project," said Vincent Wahrenburg, Project Manager at Energiequelle GmbH.
With its successful commissioning, the Krummensee turbine will make a further contribution to climate-friendly electricity generation in Brandenburg and support the expansion of renewable energy in the region. The positive development of the site is set to continue in the coming years with an additional wind turbine already planned.